Henry Street – 600 Series T-Hangars

Improvements to the Runway 15 End Safety Area (RSA) are scheduled to begin the week of July 13, 2020 and be completed by September 1, 2020.

The work includes the re-alignment of the Henry Street access road to the 600 Series T-Hangars and grading of the RSA.

Tenants will have full access to their T-hangars during construction using the existing roadway.  Once the new re-aligned roadway has been constructed, traffic will be re-routed to use the new re-aligned roadway. Then the existing roadway will be removed and graded.

This new re-aligned road will serve as a temporary access until the new permanent access is constructed as part of the New GA Terminal off Challenger Blvd. sometime in Spring/Summer 2021.