Photo by Greg HIllRunway 15-33 Rehabilitation and Extension

This project consisted of constructing a 593-foot extension on the south end of Runway 15-33 (increasing the length to 6,281 feet) and rehabilitating the existing runway pavement. This portion of the project was completed in October 2020.

In addition, Woodlawn Drive is being realigned to be outside the limits of the new Runway Protection Zone (RPZ) on the south end of Runway 33 once it is extended to the south.

Runway 4-22 Rehabilitation

This project will include the rehabilitation, not the extension, of Runway 4-22, which is 7,192 feet long.